Two thousand units at a small-appliance factory in Dongguan. Sample of 125, acceptance number 7. The report comes back from an inspection company in Guangzhou, and the conclusion line reads PASS.
The buyer books the container. But if that batch carried a 5% defect rate, the report would have passed it seven times out of ten. At 8%, it still passes two times out of ten.
Nothing went wrong with the inspection. This is how sampling is built. Nobody just shows you the table.
A Passing Report Can Sit on Top of an 8% Defect Rate
Run the common tiers of ISO 2859-1 across four lot sizes, and the same shipment lands on very different odds depending on how bad it really is:
| True defect rate | 500 units, sample 50 (Ac 3) | 1,000 units, sample 80 (Ac 5) | 2,000 units, sample 125 (Ac 7) | 10,000 units, sample 200 (Ac 10) |
|---|---|---|---|---|
| 2.5% | 96% | 98% | 99% | 99% |
| 4% | 86% | 90% | 87% | 82% |
| 5% | 76% | 79% | 71% | 58% |
| 6.5% | 59% | 58% | 43% | 24% |
| 8% | 43% | 38% | 21% | 7% |
| 10% | 25% | 18% | 6% | 1% |
Those figures are binomial, not folklore. You can reproduce them on a calculator.
There is one way to read the table: AQL 2.5 does not mean “this batch is at most 2.5% defective”. It means “this batch is probably no worse than 4%”. The stretch in between is what you are carrying.
So who set that stretch?
This Scheme Protects the Factory, Not You
When ISO 2859-1 was designed, the first number fixed was the chance of rejecting good goods. The trade calls it producer’s risk, and the convention is 5% — a batch sitting exactly on the AQL line should be waved through 95 times in a hundred. The table above runs higher than that, because acceptance numbers are whole numbers and the plans land where they land.
Your risk sits at the other end, and it is called consumer’s risk: how bad a batch has to get before it is reliably stopped. Look at the 1,000-unit row. The true defect rate has to reach 8% before the pass rate falls to 38%, and at 10% it is still 18%.
The small-lot column is worse still. A 500-unit order sampled at 50 lets a batch with 10% major defects through a quarter of the time. Nothing about that plan is broken. It is simply doing what the standard asks of it, on a lot size that cannot support much confidence.
Put plainly, sampling catches goods that are clearly broken. It does not catch goods that are not good enough. The band between those two is where sampling has nothing to say.
Most of what gets sold as reassurance in AQL sampling in China is really a division of risk. The plan decides which side of it you sit on.
In practice, when a batch fails, most buyers change inspection company rather than ask for a tighter plan. That moves the problem off the factory and onto the report.
So does more sampling make it safer?
Order Less, and the Sampling Protects You Less
Compare the first column with the last. At the same 8% true defect rate, 500 units sampled at 50 pass 43% of the time. 10,000 units sampled at 200 pass 7% of the time.

The reason is not subtle. A 50-piece sample at an 8% defect rate should contain about four defects. Let it contain three, and the batch passes. Seeing one fewer defect is not the goods getting better. It is the sample getting smaller.
This lands hardest on small buyers. A 500-unit trial order from a factory in Ningbo is exactly the order you most want to be sure about, and exactly the one sampling protects least — the same defect rate that gets stopped on a large order walks through on a small one. For a trial, tighten to Level III, set the acceptance number for major defects to zero, or inspect everything. Do not use the default.
Zero is worth understanding before you use it. On 50 pieces with an acceptance number of zero, a batch carrying 5% major defects passes 8% of the time. At 8%, it passes 2%. Setting the number to zero is the single cheapest change you can make to a trial order, and it costs nothing at the factory end.
The same plan with an acceptance number of 3 lets a 5% batch through 76% of the time. That is the whole argument in two numbers.
Sample size settled. One operational choice is left: how many times you draw.
Double Sampling Saves Hours, Not Risk
Some plans allow two draws. Inspect a small first sample, decide if you can, and only draw a second batch if the first is inconclusive. It saves inspection hours and inspection fees.
The trap is psychological. When the first draw passes, the buyer reads it as “passed on the first look, so it must be clean”. In fact the first sample in a double plan is smaller and the acceptance threshold is looser. Passing it means only that nothing obvious turned up. It does not mean the batch is cleaner than one that passed a single draw.
Save the money if you want. Just do not read “passed on the first draw” as a stronger signal. It is a weaker one.
That is where sampling stops. Four things sit outside it entirely.
Four Things AQL Cannot See
Function and life. Sampling tests the unit now, not after it has run. A motor that turns smoothly for ten minutes tells you nothing about the noise it makes at three hundred hours. That needs an aging test or a small trial batch.
Safety marks and certificates. A report can tell you whether the plug was assembled well. It cannot tell you whether the certificate is real. For CE, UL or RCM, look up the number on the issuing body’s own site. That is a separate track from sampling.
Packaging and marking. Carton dimensions, barcodes, the language on the manual, warning labels — these usually sit on a separate checklist. Sampling counts product, not cartons. Mistakes here are common and most expensive when found at the destination: two centimetres off on a carton and the whole container’s stacking plan has to be rebuilt, which costs more than the inspection did.
Consistency between batches. Inspection sees this batch. If the next one changes material, changes tooling or changes a sub-supplier, sampling will not tell you. Consistency is held by a signed first-article sample and retained batch samples, not by the table. Ask for the retained samples from the last three batches and stand them side by side — colour drift and mould wear show up faster to the eye than in any report.
None of the four is inside the sampling scope. All four are on the buyer complaint list.
So when should you drop AQL altogether?
Some Orders Should Not Use AQL
Four cases where sampling is a bad trade:
High unit value, small quantity. A hundred custom light fittings from a factory in Zhongshan, sampled at 20 under the standard tier, still pass 8% defective half the time. Whether that is a coin flip worth taking is your call, not the table’s.
Safety-critical parts. Power supplies, cells, children’s products, load-bearing structures. These are not probability problems. One failure is enough. Inspect everything, or inspect everything plus a second check on the critical items.
First orders. You have no history with this factory, and the default tier is the loosest one available. Run the first order tight and bring the second back to standard. On a first order the defects also tend to cluster — one station, one shift, one material lot — which is exactly the pattern a small sample is worst at finding.
Custom and tooled parts. On dimensions, colour and printing, a sample only tells you there is a deviation, not how much deviation counts as out of tolerance. Without a signed sample and tolerances on the drawing, sampling has nothing to judge against.
Dropping AQL does not mean dropping the standard. You still classify defects the same way; only the denominator changes from sample to whole lot.
All of that has to end up on paper.
Three Sentences for the Contract
First: write the sampling plan down. The level, the three limits, the acceptance numbers. Not “per industry practice”.
Second: write down when full inspection applies. First orders, safety parts, reworked batches. Name who pays for it in the same sentence.
Third: write down what the record has to contain. Cartons drawn, readings, defect classification, signature. Miss one and the report does not count.
None of the three is long. Together they are the only thing you can point at when the shipment is wrong.
On site, there are six questions left to ask.
Six Questions
Three for the inspection company:
- Which level is this order running, what are the acceptance numbers, and can you put the plan in writing.
- How are cartons drawn, and can you give me the draw record — which carton, which layer.
- If this batch is re-inspected, is it the same plan.
Three for the factory:
- What changed since the last batch — material, tooling, sub-suppliers.
- What are the certificate numbers on the key components, and who issued them.
- Is there anything in this lot carried over from the last one.
The first question is the easiest to fudge. “We follow the AQL standard” is not an answer. The level and the acceptance numbers are. The last question is the hardest to ask out loud, and the one that tends to produce something.
AQL is a good tool as long as you know what it stops and what it does not. It stops goods that are clearly broken. It does not stop goods that are not good enough. It protects a long, steady relationship. It does not protect a buyer placing one order.
Most AQL sampling in China that goes wrong goes wrong before the inspector arrives, in a plan nobody wrote down and a lot size nobody checked against the table.
What we do is not judge the batch for you. It is fix the sampling plan before the inspection, and leave the draw record, the readings and the defect classification inside the report, so the word “pass” has something behind it. For how to read the table and what sample size you get, see our AQL inspection guide; for what gets checked before the container leaves, see pre-shipment inspection. Within our six services, this work sits under third-party inspection.